The documents show that in March, after several weeks of problems on the rig, BP was struggling with a loss of “well control.” And as far back as 11 months ago, it was concerned about the well casing and the blowout preventer.
On June 22, for example, BP engineers expressed concerns that the metal casing the company wanted to use might collapse under high pressure.
“This would certainly be a worst-case scenario,” Mark E. Hafle, a senior drilling engineer at BP, warned in an internal report. “However, I have seen it happen so know it can occur.”
Documents
Show Early Worries About Safety of Rig – NYTimes.com